FERC is preparing an Environmental Assessment for Columbia Gas Transmission, LLC's Line 4010 Abandonment Project in Jefferson and Clarion Counties, Pennsylvania. The project would abandon in place and by removal approximately 13.7 miles of 6-inch-diameter pipeline, ten meter-stations, five mainline valves, and related appurtenances along Line 4010. The abandonment responds to a 2022 PHMSA order following an operating incident. The EA is scheduled for issuance on May 16, 2025, with a 90-day federal authorization decision deadline of August 14, 2025. This notice announces the EA preparation schedule; no impact analysis is presented.1