The Bureau of Land Management Nevada State Director issued this Notice of Intent to amend the 2008 Ely District Resource Management Plan and prepare an associated Environmental Assessment for the Robinson Summit Substation Expansion and 525 kV Interconnection Project in White Pine County, Nevada. The project covers approximately 307 acres of public land and would include a roughly 50-acre substation expansion, a new 1.3-mile single-circuit 525 kV transmission line on a 200-foot right-of-way, a new access road, and a designated utility corridor. Two alternatives are under consideration: the proposed action and no action. The scoping comment period closes June 20, 2025.12