The Nuclear Regulatory Commission issued an Environmental Assessment and Finding of No Significant Impact for Kairos Power LLC's request to amend Construction Permit No. CPTR–6 for the Hermes test reactor facility in Oak Ridge, Tennessee. The amendment extends the latest construction completion date from December 31, 2026, to April 30, 2029. Delays stem from non-nuclear demonstrations of first-of-a-kind construction techniques and more extensive site preparation than planned, including removal of legacy structures requiring coordination with the Department of Energy. The NRC concluded the amendment introduces no new construction activities, no additional land disturbance, and no significant radiological or non-radiological environmental impacts beyond those already evaluated in NUREG–2263.1234